CUSTOMER:TATA Steel UK
LOCATION:Port Talbot, Wales, UK
MATERIAL:P22 - 2.25 Chrome

challenge

• An emergency outage due to a rupture in the plant’s main descaling line

• Customer had 3 weeks to plan the outage and bring on contractors. The entire scope of work had to be completed in under 2 weeks

results

Liburdi performed a scale mock up of the application which simulated clearance restrictions and pre-heat conditions. Weld technique sheets were developed and locked-in all welding parameters and equipment configuration ahead of execution.

• Fast tracked UK visas and work permits for site execution team

• Completed the original and additional scope within the customers demanding time frame

• All welds passed inspection the first time with no repairs needed